Delivery & Installation Guide
Receiving project cabinetry is not only a matter of checking whether cartons arrived.
For contractors, designers, developers and international buyers, the receiving process should confirm what was delivered, what condition it arrived in, whether any exceptions need to be recorded, and whether the shipment is ready to move into installation.
The purpose of receiving inspection is not to assign responsibility immediately.
It is to create a clear record of:
-
Shipment condition
-
Quantity
-
Labels and cabinet codes
-
Visible and concealed damage
-
Shortages or incorrect items
-
Document discrepancies
-
Packaging condition
-
Installation readiness
-
Unresolved exceptions
Any reporting deadline should follow the applicable contract, carrier documents, delivery receipt, insurance requirements and local rules. Do not assume that one fixed reporting period applies to every project.
Prepare the Receiving Documents Before Arrival
Before the shipment reaches the project site, prepare the documents needed for checking.
Depending on the agreed project and delivery scope, these may include:
-
Commercial invoice
-
Packing list
-
Bill of lading or other transport document
-
Delivery order
-
Delivery receipt
-
Cabinet or room schedule
-
Approved drawings
-
Carton or package list
-
Hardware or accessory list
-
Relevant shipping instructions
-
Project contact list
-
Exception-reporting contact details
The project team should know which document will be used as the receiving reference before unloading begins.
Check the Vehicle, Container or Seal Where Applicable
Where the delivery method allows it, record the condition of the transport unit before unloading.
Check and document:
-
Vehicle or container identification
-
Seal number, where applicable
-
Whether the seal appears intact
-
Visible external impact
-
Water ingress or unusual moisture
-
Container or vehicle door condition
-
Major deformation
-
Signs of load movement
-
Unusual carton displacement near the opening
Take wide photographs before packages are moved.
If an irregular condition is visible, record it before unloading continues.
Review the Bill of Lading or Delivery Receipt
The transport document or delivery receipt should be reviewed at the time of handover.
Check:
-
Shipment or consignment reference
-
Number of packages shown
-
Delivery date and time
-
Visible exceptions
-
Shortage notes
-
Damaged packaging notes
-
Seal or vehicle information where relevant
-
Consignee or receiving-party information
If visible damage or shortages are identified during handover, record them according to the applicable delivery documents and project procedure.
Do not rely only on verbal discussion.
Check the Packing List
Use the packing list as one of the main references for receiving.
Confirm:
-
Total package count
-
Room identification
-
Unit or apartment number where applicable
-
Cabinet codes
-
Carton numbers
-
Accessory cartons
-
Hardware packages
-
Loose panels
-
Glass, mirrors or other fragile components
-
Special items
Do not combine all packages into one count if the project requires room-by-room or unit-by-unit control.
Confirm Carton, Room, Unit and Cabinet Codes
Before cartons are distributed around the site, verify that the labels correspond with the project documents.
Check:
-
Room code
-
Unit code
-
Cabinet code
-
Carton number
-
Quantity
-
Drawing reference if shown
-
Hardware or accessory identification
Unclear or missing labels should be photographed before the package is moved or opened.
Where possible, keep items grouped by room, unit or cabinet code.
This reduces the risk of installers mixing components from different areas.
Check Quantity, Shortages and Incorrect Items
Compare the physical shipment against the packing list and approved project information.
Record:
-
Missing cartons
-
Extra cartons
-
Incorrect labels
-
Duplicated items
-
Wrong cabinet codes
-
Missing hardware packages
-
Missing accessories
-
Items assigned to the wrong room or unit
A package count alone does not confirm that every required component is present.
Large panels, doors, small hardware, accessories and loose components may need separate checks.
Inspect Visible Damage Before Unpacking
Check the outside of each package before opening.
Look for:
-
Crushed corners
-
Punctures
-
Torn cartons
-
Wet packaging
-
Open cartons
-
Broken strapping
-
Damaged pallet corners
-
Compression marks
-
Heavy impact
-
Shifted loads
-
Damaged edge protection
Take both:
-
Wide photographs showing the full package
-
Close-up photographs showing the specific condition
Record the carton or package number in the same evidence set.
Inspect for Concealed Damage After Opening
External packaging may look acceptable while internal parts have been affected.
After unpacking, check:
-
Panel corners
-
Door surfaces
-
Drawer fronts
-
Edges
-
Glass
-
Mirrors
-
Hardware
-
Shelves
-
Exposed panels
-
Decorative finishes
-
Countertops where applicable
Possible issues may include:
-
Chips
-
Cracks
-
Scratches
-
Dents
-
Swelling
-
Staining
-
Finish mismatch
-
Broken glass
-
Damaged hardware
-
Deformation
-
Loose fittings
Do not mix concealed transport damage, manufacturing quality issues and installation damage into the same category.
Record the observed condition first, then allow the relevant project parties to review the cause and responsibility.
Create Photo, Video and Document Evidence
A useful receiving record should connect each issue with the relevant item.
Where practical, record:
-
Carton number
-
Cabinet or part code
-
Room or unit
-
Photo file reference
-
Video reference
-
Issue description
-
Observed condition
-
Date
-
Receiving location
For significant exceptions, include:
-
Wide view of the shipment or package
-
Label photograph
-
Close-up of the issue
-
Another angle showing scale or location
-
Unpacked item where relevant
Avoid repairing, disposing of or altering evidence before the issue has been reviewed.
Retain Packaging Where Required
Packaging can help clarify how an item was protected and where damage may have occurred.
For affected items, retain relevant packaging where practical until the exception has been reviewed.
This may include:
-
Cartons
-
Corner protection
-
Foam
-
Straps
-
Pallet material
-
Internal separators
-
Labels
Do not discard important packaging immediately when a claim, inspection or responsibility review may still be required.
Record OSD Exceptions
OSD commonly refers to:
Overage, Shortage and Damage.
A project receiving record may separate exceptions into:
-
Overage
-
Shortage
-
Visible damage
-
Concealed damage
-
Incorrect item
-
Incorrect label
-
Document discrepancy
-
Missing accessory
-
Unclear status
Each exception should have its own record rather than being hidden inside general receiving notes.
Quarantine Items That Should Not Enter Installation
Some items should be separated from normal installation flow while they are being reviewed.
A quarantine area or clear hold label can be used for items such as:
-
Damaged panels
-
Incorrect items
-
Unidentified cartons
-
Wet packages
-
Parts with unresolved dimensional concerns
-
Components awaiting replacement decision
Quarantine does not automatically determine who is responsible.
It simply prevents unresolved items from being installed or mixed with accepted components.
Use Release, Partial Release or Hold Status
After receiving inspection, the project team can classify the shipment or area into one of three working statuses.
Release
The checked items are suitable to proceed to the next planned stage, subject to normal installation checks.
Partial Release
Some items can proceed, while identified exceptions remain separated and recorded.
Hold
Installation or distribution should not proceed for the affected items until the exception has been reviewed.
These statuses help separate receiving control from final responsibility decisions.
Define Installation-Release Conditions
Cabinetry should not move into installation simply because it has arrived.
Before release to installers, confirm the relevant conditions, such as:
-
Required quantities have been checked
-
Room or cabinet codes are clear
-
Major visible exceptions are recorded
-
Critical damaged items are separated
-
Required installation drawings are available
-
The correct drawing revision is being used
-
Appliance information is confirmed where relevant
-
Site access is ready
-
Walls, floors and service points are ready where required
-
Unresolved items that may affect installation have been identified
The exact release conditions depend on the project and installation responsibility.
Responsibility Matrix
Packing Documents
Supplier / Production Side:
Provide packing documents according to the confirmed supply scope.
Buyer / Project Team:
Review documents before delivery.
Carrier / Delivery Party:
Provide applicable transport handover documents.
Local Contractor / Installer:
Support site receiving where assigned.
Packing List
Supplier / Production Side:
Provide the applicable packing list.
Buyer / Project Team:
Use the packing list for receiving checks.
Local Contractor / Installer:
Use room, unit or cabinet information where relevant.
Transport Handover
Supplier / Production Side:
Coordinate according to the agreed delivery scope.
Buyer / Project Team:
Coordinate receiving arrangements.
Carrier / Delivery Party:
Provide transport handover documentation and participate in handover according to the applicable transport process.
Local Contractor / Installer:
Support site access where assigned.
External Package Condition
Supplier / Production Side:
Review evidence if an exception is reported.
Buyer / Project Team:
Record package condition during receiving.
Carrier / Delivery Party:
Participate in review where transport responsibility applies.
Local Contractor / Installer:
Support documentation where assigned.
Quantity Check
Supplier / Production Side:
Provide reference documents for the confirmed supply scope.
Buyer / Project Team:
Lead or coordinate the receiving check.
Local Contractor / Installer:
Support room or site distribution where assigned.
Damage Evidence
Supplier / Production Side:
Review submitted evidence for supplied items.
Buyer / Project Team:
Record and retain relevant evidence.
Carrier / Delivery Party:
Review where transport responsibility applies.
Local Contractor / Installer:
Avoid altering relevant evidence before review.
Manufacturing Quality Issue
Supplier / Production Side:
Review the supplied item against the approved project information.
Buyer / Project Team:
Record and report the observed condition.
Local Contractor / Installer:
Report the issue before installation if it is identified at the site.
Installation Damage
Buyer / Project Team:
Coordinate review of the issue.
Local Contractor / Installer:
Record and review installation-stage damage where applicable.
Quarantine
Supplier / Production Side:
Support review and clarification where required.
Buyer / Project Team:
Coordinate hold status.
Local Contractor / Installer:
Do not install held items.
Release Decision
Supplier / Production Side:
Provide clarification where required.
Buyer / Project Team:
Coordinate the project release decision.
Local Contractor / Installer:
Proceed only with released items.
The actual project responsibility should follow the contract, commercial terms, shipping documents, handover records and local installation arrangements.
Report Exceptions and Track Them to Closure
An exception record should remain open until the project team has agreed on the next action.
A simple exception log may include:
-
Issue number
-
Date
-
Room or unit
-
Carton or part code
-
Issue category
-
Photographs
-
Current status
-
Responsible review party
-
Proposed action
-
Replacement or repair status
-
Closure date
-
Closure evidence
Possible actions may include:
-
Clarification
-
Additional inspection
-
Replacement
-
Repair
-
Local adjustment
-
Partial installation
-
Return
-
Acceptance as recorded
Responsibility should not be assumed before the relevant evidence and project documents are reviewed.
Practical Receiving Checklist
Before installation release, check:
-
Pre-arrival documents are available
-
Vehicle, container or seal condition has been recorded where applicable
-
Delivery receipt or transport document has been reviewed
-
Packing list is available
-
Package count has been checked
-
Room, unit and cabinet codes have been checked
-
Missing or incorrect items have been recorded
-
Visible package damage has been photographed
-
Concealed damage has been checked after unpacking
-
Photo and video evidence is linked to the relevant item
-
Important packaging has been retained where required
-
OSD exceptions have been recorded
-
Held items have been quarantined
-
Release, Partial Release or Hold status has been assigned
-
Installation-release conditions have been reviewed
-
Open exceptions have an owner and next action
Request a Detailed Project Quote
If you are planning a custom cabinetry or whole-home furniture project, you can provide the available drawings, room information, dimensions, delivery location and project requirements for review.
Request a Detailed Project Quote →
The final supply, transport, receiving and installation responsibilities depend on the confirmed quotation, approved drawings, shipping documents and written project agreements.